Rationale for this Project


Summary of Progress during October – December 2016
  1. This project retained some of its prominence, but not to the degree of previous quarters.
  2. A continuing disappointment was that I didn’t pursue my web-training with Sitepoint, despite having – in anticipation – extended my membership for another couple of years. I have, however, grabbed all the eBooks in their library, though haven’t catalogued them all yet.
  3. However, Nat discovered a course put out by Harvard - "Harvard University - CS50 Introduction to Computer Science" - which he has been pursuing vigorously and finding very helpful. I’ve taken a look at it and hope to take the course as well, though at a more leisurely pace over the coming year.
  4. I completed tidying up the work on "Mansell (Peter) - Bottom Up Reading of Acts".
  5. Otherwise there was rather a random scatter of stuff, as can be seen from the detailed list below.
  6. During 4Q16 I expended 153 hours on this project (153 hours YTD, where for “YTD” – Year to Date – I mean the academic year that commenced in October 2016). That’s 83% of planned effort, 83% YTD. Overall, 24% of my project effort in the Quarter was directed towards this Project (making 24% YTD) – as against 30% planned (30% YTD).
  7. Full details for 4Q16 are given below:-

Website (Total Hours = 50.25)
  1. Website - Bridge Development (Total Hours = 16.5)
    • Bridge - Butler IMPs - ECL Discussions & Testing (7.5 hours)
    • Bridge - Butler IMPs - Fixes for Teams of 8 webpage EW half-way switch (Fletcher) (1.75 hours)
    • Bridge - Butler IMPs - Fixes for Teams of 8 webpage output names (Fletcher) (1 hour)
      → See "Software Development - Website - Development"
    • Bridge - Website - Automate width of "Average Percentages by Partner, By Quarter" page (0.75 hours)
    • Bridge - Website Update (5.5 hours)
      → See "Admin - Bridge - Admin"
  2. Website - Development (Total Hours = 8.75)
    • Website - Generator - Add clearer links to other versions of Notes "up front" (2.5 hours)
    • Website - Generator - Bug where line starts with +NnnnN+. (0.5 hours)
    • Website - Generator - Documenter - Database tidy-up (0.25 hours)
    • Website - Generator - Move quotations to outside the links to papers (0.25 hours)
    • Website - Generator - Optional regeneration of Abstracts with embedded Notes - for Temp Notes (0.5 hours)
    • Website - Generator - Problem with recording actuals - books and papers (1 hour)
    • Website - Generator - Spider - fix re .shtm / .shtml (0.25 hours)
    • Website - Generator - Spider External Links: Correction Aids (0.75 hours)
    • Website - Generator - WebRefs - Fix for "HTTP as text rather than reference prefix (2 hours)
    • Website - Generator - WebRefs - Fix for Notes (0.75 hours)
      → See "Software Development - Website - Development"
  3. Website - Education (Total Hours = 13.75)
  4. Website - Infrastructure (Total Hours = 4.5)
  5. Website - Maintenance (Total Hours = 6.75)

Website Others (Total Hours = 102.75)
  1. Website Others - Bernie's Website Development (Total Hours = 11.75)
  2. Website Others - ECBA Maintenance (Total Hours = 28.75)
  3. Website Others - ECBA Membership - Development
  4. Website Others - Enigma Ensemble
  5. Website Others - Joint Project Data Analysis
    • Bridge - Joint Project - Data Modelling - Blog creation (2.25 hours)
  6. Website Others - Joint Project Data Collection (Total Hours = 18.25)
    • Bridge - Joint Project - Data Collection & "Mini Website" output (17.75 hours)
    • Bridge - Joint Project - Trouble with Apple (0.5 hours)
      → See "Admin - Bridge - Joint Project"
  7. Website Others - Pete's PhD (Total Hours = 31.75)
    • Mansell (Peter) - Bottom Up Reading of Acts - Appendices: Set up live site (4.25 hours)
    • Mansell (Peter) - Bottom Up Reading of Acts - Appendices: Stats Generation (26.25 hours)
    • Mansell (Peter) - Bottom Up Reading of Acts - Appendices: True up Greek + English (1.25 hours)
      → See "Mansell (Peter) - Bottom Up Reading of Acts"

Plans for the Near Future

I’ve retained the planned weekly effort on this project at 14 hours. My intention over the next two years is to reduce the amount of effort expended on other sites and focus on sorting out my own, together with updating my technical competence. To avoid too long a straggle of items on this report, I’ve created a document9 listing outstanding items10, together with those completed since the document was created. As a result, only the more important11 items likely to be addressed shortly appear below.
Summary of Progress to Date

This is hived off to a separate13 document14. A summary of time expended across the years developing my website15 is at "Software Development - Website - Development".



In-Page Footnotes

Footnote 4: Footnote 5: This is very tedious to produce and consequently is both incomplete and out of date.

Footnote 7: Footnote 10: This hasn’t been updated since the end of last year, but hasn’t needed to change much.

Footnote 11: This list has, however, got too long!

Footnote 12: Footnote 13: Footnote 15: As distinct from developing other peoples’ websites – time which is also recorded against this project, but not against this task.


Live Version of this Archived Note

Date Length Title
20/07/2017 14:34:05 11297 Status: Web-Tools (2017 - June)


Table of 12 Earlier Versions of this Note (of 63)

Date Length Title
14/10/2016 22:14:53 14567 Status: Web-Tools (2016 - September)
21/07/2016 16:12:00 13206 Status: Web-Tools (2016 - June)
05/04/2016 23:19:41 15377 Status: Web-Tools (2016 - March)
07/01/2016 00:59:02 15186 Status: Web-Tools (2015 - December)
07/10/2015 00:27:22 15018 Status: Web-Tools (2015 - September)
02/07/2015 23:12:29 13706 Status: Web-Tools (2015 - June)
23/04/2015 21:14:24 11896 Status: Web-Tools (2015 - March)
13/01/2015 19:07:41 9750 Status: Web-Tools (2014 - December)
07/10/2014 17:39:50 9802 Status: Web-Tools (2014 - September)
04/07/2014 22:46:34 9755 Status: Web-Tools (2014 - June)
04/04/2014 19:03:22 8926 Status: Web-Tools (2014 - March)
14/01/2014 17:57:07 8091 Status: Web-Tools (2013 - December)


Later Version of this Note

Date Length Title
10/04/2017 23:38:24 11470 Status: Web-Tools (2017 - March)



This version updated Reference for this Topic Parent Topic
14/01/2017 20:18:14 520 (Status: Web-Tools (2016 - December)) Status: Summary (2017 - June)



Summary of Notes Links from this Page

Internet Technology and Philosophy Research - Internet Technology Research - Proposal Status: Web-Tools (Summary of Progress to Date) Theo Todman's Websites Maintained
Website - Outstanding Developments (2016 - September) Website Generator Documentation - Control Page . . .

To access information, click on one of the links in the table above (if any).




Summary of Note Links to this Page

Status: Consciousness Studies (2016 - December) Status: Personal Identity (2016 - December) Status: Summary (2016 - December), 2 Status: Summary Task List (2016: October - December)  

To access information, click on one of the links in the table above (if any).




Text Colour Conventions

  1. Blue: Text by me; © Theo Todman, 2017




© Theo Todman, June 2007 - August 2017.Please address any comments on this page to theo@theotodman.com.File output:
Website Maintenance Dashboard
Return to Top of this PageReturn to Theo Todman's Philosophy PageReturn to Theo Todman's Home Page